| Lighting Project Update - 17 June 2009 |
| Wednesday, 17 June 2009 | |
|
Our lights project will formally commence on Tuesday 23 June when footings for the four poles will be dug and the concrete poured. The poles are expected to arrive on site shortly after, or at the same time.
Work will continue for the rest of next week and the following week, which is the first week of the school holidays. Work will then need to stop for the second week of the school holidays because of the Southern Skies tournament. The following week, starting Monday 13 July, may require us to cancel all but Premier League team training as there will be only limited power each night. This will give the contractors every chance to complete the work as soon as possible. We would like to thank all members and their families for their patience and understanding during this large and important project. |